Skip navigation
st. Mary's University Institutional Repository St. Mary's University Institutional Repository

Please use this identifier to cite or link to this item: http://hdl.handle.net/123456789/3252
Title: ASSESSMENT OF USING SCOPE AND TIME MANAGEMENT TOOLS AND TECHNIQUES IN ETHIOPIAN POWER TRANSMISSION PROJECTS
Authors: DELESSA, TESFAYE
Keywords: Project scope management
Project time management
Relative Use Index
Tools and techniques of project management
Issue Date: Jun-2017
Publisher: St.Mary's University
Abstract: The application of Project Management Tools and Techniques (PMTT) will have potential benefits for increased efficiency, improved project predictability, increased stakeholders confidence, improved communication, and increased probability of project success. Proper management of project scope and time tools and techniques can help project success with standard expectations. However, in most cases the Ethiopian Power Transmissions Projects do not seem making their deadlines. The objective of this paper is to investigate the extent to which project scope and time management tools and techniques are used in power transmission projects in Ethiopia. The study employed descriptive and explanatory research design using primary and secondary data. The data for this study was obtained through questionnaires and interviews. The survey questions were distributed to 60 client, consultant and contractor professionals working on Ethiopian power transmission projects. The respondents were selected using expert and purposive sampling techniques. Interviews were conducted with two project managers to triangulate and supplement the data obtained from the questionnaires. The responses were analyzed and interpreted using SPSS analytical tools. The results of the findings of the study indicated that scope and time management tools and techniques are not effectively utilized for Ethiopian Power Transmission Projects. Based on the findings the conclusion drawn is the constraints for keeping usage of scope and time management tools and techniques to low level are management, organizational, and human. Based on the findings it is recommended companies in power transmission projects address the constraints to make use of customized scope and time management tools and techniques. The results of the study will help companies involved in power transmission projects to improve their level of using project scope and time management tools and techniques and the study lays foundation for further researches. Hence the result of this study will be communicated to companies involved in Power Transmission projects in Ethiopia.
URI: .
http://hdl.handle.net/123456789/3252
Appears in Collections:Project Management

Files in This Item:
File Description SizeFormat 
Final Thesis Tesfaye Delessa 08.07.2017.pdf727.88 kBAdobe PDFView/Open
Show full item record


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.