dc.description.abstract | The purpose of carrying out this study was to assess the performance of government precast
technology housing projects in Addis Ababa using the case of the case of Kirkos Sub-City
Woreda 06 Kasanchis Building Project. Descriptive research design and mixed approach were
employed as a methodology for this study. The project performance was assessed in terms of the
PMBOK knowledge areas of the project process groups using project quality and time
management. The study used primary and secondary data sources. Primary data has been
collected through in-depth interviews and observation. Structure and unstructured interviews
were administered to all 24 key personnel from all three parties involved in the Kirkos Sub-City
Woreda 06 Kasanchis Building Project. The findings of the study showed that even though
project performance in terms of project quality management and project time management
specifically as it pertains to the government funded housing projects using precast technology in
Addis Ababa was very promising in terms of adhering to the fundamental principles of project
management, it was still faced with an array of challenges that were quite similar to those
housing projects using the conventional type of construction methods. Generally, the researcher
concluded that, the performance of project using the aforementioned technology had a better
result in terms of quality management but had various issue when it comes to time management
and attaining a poor performance as a result. Finally, this study suggested to all the project
implementers at each level, that although there were significant challenges faced with regards to
the performances of the project in case in terms of quality and time and even though
implementing such project won’t render a quick fix to the housing problems in Addis Ababa,
there are plenty good experiences of that can be taken on board to help serve as a learning curve
for future endeavors | en_US |
dc.language.iso | en | en_US |
dc.publisher | St. Mary’s University | en_US |
dc.subject | Project, Project management, Project performance, Quality management, Time management | en_US |